Zuschlag erteilt Offenes Verfahren (EU-weit) · veröffentlicht am 11.02.2022

81280949-Pool d'experts : développement organisationnel, régulation, maîtrise d'ouvrage et ingénierie dans le secteur de l'eau

Auftraggeber: Deutsche Gesellschaft für Internationale Zusammenarbeit (GIZ) GmbH · Eschborn

Deutsche Gesellschaft für Internationale Zusammenarbeit (GIZ) GmbH hat den Auftrag für Wasser- und Energieversorgung in The Democratic Republic of the Congo am 06.07.2022 vergeben, Zuschlag an Ambero Consulting Gesellschaft mbH. Zuschlagssumme nach den Angaben der Bekanntmachung: 2.152.350 €. Eingegangen: 3 Angebote.

Zuschlag an

Ambero Consulting Gesellschaft mbH Kronberg i. Ts

Summe
2.152.350 €
Angebote
3
Zuschlag
06.07.2022

Quelle: Bekanntmachung auf TED (© Europäische Union), veröffentlicht am 12.07.2022.

Angaben in Kürze

Aus den Feldern, ohne KI
Was
Wasser- und Energieversorgung: 81280949-Pool d'experts : développement organisationnel, régulation, maîtrise d'ouvrage et ingénierie dans le secteur de l'eau
Wo
The Democratic Republic of the Congo
Wer kann anbieten
Jedes Unternehmen, das die Anforderungen der Vergabeunterlagen erfüllt.
Laufzeit
01.05.2022 bis 30.11.2024

Automatisch aus den Feldern der Bekanntmachung vom 12.07.2022, ohne KI. Die Branche ordnen wir selbst zu. Maßgeblich ist die Bekanntmachung. Original lesen ↗ · Fehler melden

Leistungsumfang

Beschreibung laut Bekanntmachung

With about 52% of Africa's surface water reserves and 23% of its renewable water resources, Democratic Republic of Congo (DRC), is Africa's richest country. Nevertheless, at the national level, only 33% of the population, including 52% in urban areas and only 19% in rural areas, have access to an improved supply of drinking water. Among the country's 26 provinces, there are large differences in improved access to safe drinking water. Only five provinces have an urban access rate of more than 50%, including South Kivu (64%), one of the project's partner provinces. The other partner provinces have an access rate not exceeding 35%. DRC is also one of the poorest countries in the world with a poverty rate of about 63% and an average annual gross domestic income per person of USD?1,063. Only 17% of poor households have access to safe drinking water, while 82% of the richest households have …

Ganze Beschreibung lesen

With about 52% of Africa's surface water reserves and 23% of its renewable water resources, Democratic Republic of Congo (DRC), is Africa's richest country. Nevertheless, at the national level, only 33% of the population, including 52% in urban areas and only 19% in rural areas, have access to an improved supply of drinking water. Among the country's 26 provinces, there are large differences in improved access to safe drinking water. Only five provinces have an urban access rate of more than 50%, including South Kivu (64%), one of the project's partner provinces. The other partner provinces have an access rate not exceeding 35%. DRC is also one of the poorest countries in the world with a poverty rate of about 63% and an average annual gross domestic income per person of USD?1,063. Only 17% of poor households have access to safe drinking water, while 82% of the richest households have access to it. Women and girls also suffer particularly from poor access to safe drinking water, as they"re traditionally responsible for the time-consuming supply of household water. The political and humanitarian situation in the DRC remains very tense. Water supply infrastructures are almost exclusively financed (about 95%) by international development partners and is mainly owned by the main public water operator (REGIDESO) which is being privatized. There are also small private water operators/suppliers and local non-governmental organizations as well as user associations. With the Water Law of 2015, project management of the sector is delegated to the provinces. The provincial technical structures that should take over this responsibility are under construction. The complementary structures necessary for the liberalization of the sector have yet to be put in place, such as the Public Water Service Regulatory Authority (ARSPE). The National Water Service Policy (PNSPE) exists but is still awaiting validation by the Ministry of Water Resources and Electricity. REGIDESO, has been undergoing a reform and restructuring process for some time, which is not progressing as planned. Water supply, especially for the poor population in provincial cities, cannot be guaranteed sustainably by REGIDESO in its current configuration The objective of the project "Strengthening the Efficiency of Drinking Water Services in the DR Congo" is therefore to improve institutional conditions to ensure a high-quality, sustainable and inclusive urban water supply. The project is financed by the German Federal Ministry for Economic Cooperation and Development (BMZ) and the U.S. Agency for International Development with a duration from January 2022 to December 2024. It contributes to the effort of the Congolese Government to improve access to drinking water. The project supports on one hand the increase of performance of REGIDESO (component 1) and on the other hand the capacity development of institutions at central (component 3) and decentralised (component 2) level; including the regulation of the sector. The project works to strengthen accountability between local authorities, the population and the private sector. This tender aims a substantial contribution to all components.

Erfüllungsort

Ort
The Democratic Republic of the Congo
NUTS
CD

Verlauf

  1. 11.02.2022 Ausschreibung veröffentlicht
  2. 12.07.2022 Ergebnis veröffentlicht

Häufige Fragen

Wer hat den Auftrag bekommen?

Den Zuschlag hat Ambero Consulting Gesellschaft mbH erhalten, Summe 2.152.350 €.

Quellen Bekanntmachung auf TED ↗ Daten: TED – Tenders Electronic Daily, © Europäische Union, Weiterverwendung mit Quellenangabe. Namen und persönliche Kontaktdaten von Ansprechpersonen entfernen wir automatisch. Ist uns etwas entgangen? Fehler melden

Ähnliche offene Ausschreibungen

Endet bald Lieferung Ökostrom 2027
Hamburger Energienetze GmbH
03.11.2026 noch 2 Tage
3,65 Mio. € Wert, geschätzt
Hamburg Hamburg
Endet bald Verteilungsverfahren Sondernutzung von Flächen für E-Ladeinfrastruktur
Stadtverwaltung Ingelheim am Rhein
05.11.2026 noch 4 Tage
nicht angegeben Wert, geschätzt
Ingelheim am Rhein Rheinland-Pfalz
Endet bald Stromlieferung im Zuständigkeitsbereich des RB Süd der LSBB
Landesstraßenbaubehörde Sachsen-Anhalt RB Süd
05.11.2026 noch 4 Tage
nicht angegeben Wert, geschätzt
Halle (Saale) Sachsen-Anhalt

Weitere Zuschläge dieses Auftraggebers

Von hier aus weiter